Environmental Site Assessment and Investigation

Phase I Environmental Assessment of Site for Remanufacturing of Waste Toner Cartridges

  • Year

    2019

  • Client

    Confidential

  • Country

    Serbia

  • Subcontracted by

    Ramboll (USA)

Scope/our task: Phase I environmental assessment and limited environmental compliance assessment of site for remanufacturing of waste toner cartridges.

Phase I and Phase II Environmental Assessment of Site for Plastic Products Manufacturing

  • Year

    2018-2019

  • Client

    Confidential

  • Country

    Serbia

Scope/our task: Phase I environmental assessment of site for plastic products manufacturing by injection moulding, extrusion and blowing for buy-side. Limited Phase II involved installation of groundwater monitoring wells, and soil and groundwater sampling.

Soil and Groundwater Assessment of Automotive Components Production Site, Kragujevac

  • Year

    2018

  • Client

    Confidential

  • Country

    Serbia

  • Subcontracted by

    ERM (Germany)

Scope/our task: Site for production of cold-end exhaust systems and plastic components and modules. Desktop environmental site assessment for buy-side.

Environmental Assessment of the Belgrade “Nikola Tesla” Airport Operations

  • Year

    2017

  • Client

    Incheon International Airport Corporation

  • Country

    Serbia

  • Subcontracted by

    Keunjeong Architects (South Korea)

Scope: Supplement to the Technical Proposal of the Incheon International Airport Corporation’ Concession Bid. Environmental assessment of the airport operations and proposal of the environmental technical improvements over the 25-years concession period, in cooperation with the Environmental Team of Incheon Airport.
Our task: Solid Waste Management and Disposal Strategy, Noise Monitoring and Mitigation Plan, Environment Health and Safety Strategy, Community Engaging Strategy, Contingency Runway Environmental Assessment.

Environmental Site Assessment and Limited Groundwater Investigation of Brownfield Site in Niš

  • Year

    2012

  • Client

    Confidential

  • Country

    Serbia

  • Contracted by

    Confidential

Project scope/our task: InSitu was commissioned by a global automotive manufacturer to perform the environmental assessment of the site in Niš considered for acquisition. The service included Phase I ESA and installation of monitoring wells, groundwater sampling and analysis to evaluate potential historical contamination.

Regional Solid Waste Management Scheme in Pirot District – Master Plan for Closure of Non-Sanitary Waste Landfills

  • Year

    2011-2012

  • Client

    EU Commission

  • Country

    Serbia

  • Consortium

    Eptisa, Royal HaskoningDHV, VNG

Project area: Municipalities of Pirot, Dimitrovgrad, Babusnica, Bela Palanka (South-East Serbia);
Project scope: Closure of the existing municipal dumpsites in four municipalities. Based on the risk assessment and results of performed investigation the cost-efficient measures for landfill closure were proposed. A component of the MISP programme (Municipal Infrastructure Support Programme) which assists municipalities in Serbia in the preparation of project documentation and implementation of municipal infrastructure projects. Financed by the EU under the IPA 2008 Programme.
Our task: Environmental baseline analysis, risk assessment, management of field investigations and evaluation of results, proposal of the closure plan.

Design and Installation of Groundwater Monitoring Network in “Holcim” Cement Plant, Novi Popovac

  • Year

    2010-2011

  • Client

    Holcim Serbia

  • Country

    Serbia

  • Consortium

    Holcim Serbia

Project scope: InSitu was commissioned by Holcim to establish the groundwater monitoring at the cement plant site in Novi Popovac and at the adjacent abandoned industrial landfill. The scope of work included installation of 14 monitoring wells at the plant site, sampling and analysis of 30 wells, evaluation of the results, preparation of conceptual hydrogeological model, etc.

Phase I & Phase II Environmental Assessment of Greenfield Site in Belgrade

  • Year

    2010

  • Client

    Confidential

  • Country

    Serbia

  • Subcontracted by

    Golder Associates (Germany)

The Client (global wholesaler) asked for the environmental site assessment and soild and groundwater sampling at a site in Belgrade, Serbia planned for development of a Cash&Carry market.

Phase I & Phase II Environmental Assessment of Greenfield Site in Subotica

  • Year

    2010

  • Client

    Confidential

  • Country

    Serbia

  • Subcontracted by

    Golder Associates (Germany)

The Client (global wholesaler) asked for the environmental site assessment and soild and groundwater sampling at a site in Subotica, Serbia planned for development of a Cash&Carry market.

Phase I Environmental Assessment of a Heavy Vehicle Repair and Maintenance Site in Sarajevo

  • Year

    2010

  • Client

    Confidential

  • Country

    Bosnia and Herzegovina

  • Subcontracted by

    Confidential

Project scope/our task: InSitu was commissioned by a global automotive producer to perform the Phase I ESA of the site in Sarajevo considered for acquisition.

Phase I Environmental Assessment of a Heavy Vehicle Repair and Maintenance Site in Belgrade

  • Year

    2009

  • Client

    Confidential

  • Country

    Serbia

  • Subcontracted by

    Confidential

Project scope/our task: InSitu was commissioned by a global automotive producer to perform the Phase I ESA of the site in Belgrade considered for acquisition.

Phase I Environmental Assessment of Greenfield Site in Skopje

  • Year

    2008

  • Client

    Confidential

  • Country

    Macedonia

  • Subcontracted by

    Golder Associates (UK)

Project scope/our task: A real estate client asked for the environmental assessment of a greenfield site in Skopje, Macedonia considered for development.

Phase I Environmental Assessment of Carbon-Steel Production and Retail Sites in Belgrade

  • Year

    2008

  • Client

    Confidential

  • Country

    Serbia

  • Subcontracted by

    Confidential

Our task: InSitu was commissioned by a global steel producer to perform the Phase I ESA of three sites (production and retail) in Belgrade, considered for acquisition.

Phase I Environmental Assessment of Disused Ferrochromium Production Site in Dugi Rat

  • Year

    2007

  • Client

    Confidential

  • Country

    Croatia

  • Subcontracted by

    Golder Associates (UK)

Project scope/our task: A real estate client asked for the environmental assessment of the brownfield site in Dugi Rat, Croatia considered for redevelopment.

Phase I Environmental Assessment of Greenfield Site in Hvar

  • Year

    2007

  • Client

    Confidential

  • Country

    Croatia

  • Subcontracted by

    Golder Associates (UK)

Project scope/our task: A real estate client asked for the environmental assessment of the greenfield site in Hvar, Croatia considered for development.

Phase I Environmental Site Assessment of Eleven Real Estate Properties in Belgrade and Niš

  • Year

    2007

  • Client

    Confidential

  • Country

    Serbia

  • Subcontracted by

    Golder Associates (UK)

Project scope/our task: A global investment bank asked for the environmental assessment of eleven sites in Belgrade and Niš (Serbia) considered for commercial development.